Scrum for Team System Guidance / Version 3 / Release
Work Item: Release
Description:
The Release work item is the primary element of the project planning scope. Working with linked Sprint items, it displays rolled up information on the release duration and backlog work loads currently planned and completed.
Calculated values:
The release work item includes several calculated fields. The values of theses fields are generated from both linked sprints and Product Backlog Items that have a planning scope that resides beneth the release.
For Example: A PBI with a planning scope of "Project/Release 1/Workstream/Sprint 1/Team A" will contribute to a release with a planning scope of "Project/Release 1/"
Screen Shot:

Fields:
| Field Name | Description | Data Type |
|---|---|---|
| Release Name | The planning scope (AKA Iteration Path) of the release. | Project Path |
| Current Status | The release status. | Drop Down List |
| Release Audience |
The intended audience of this release. Possible values are:
|
Drop Down List |
| Estimated Capacity | The estimated number of Story Points planned for this release | Number |
| Planned Work | The total number of story points of Product Backlog Items under this release. | (Calculated) Number |
| Burned Work | The number of story points done in this release. Calculated from the sum of all Product Backlog Items under this release in a state of "Done". | (Calculated) Number |
| (Planned Duration) Work Starts | The planned starting date for this release. | Date Time |
| (Planned Duration) Work Ends | The planned end date for this release. | Date Time |
| (Planned Duration) Go Live Date | The go live date for this release. This is useful if the end and go live dates differ. | Date Time |
| (Actual Duration) Work Starts | Calculated from the earliest start date of all the linked sprints. | (Calculated) Date Time |
| (Actual Duration) Work Ends | Calculated from the latest end date of all the linked sprints. | (Calculated) Date Time |
| Release Goal | Use this field to describe the target goal of this release. | Text |
Life Cycle Tracking:

Work flow: