Scrum for Team System Guidance / Version 3 / Impediment

Work Item: Impediment

Description:

The impediment work item is used to describe situations that are stopping the completion of work on a Product Backlog Item. Impediments have their own unique relationship with PBIs using the "Impedes" linkage type. When this linage is used, the status of the impediment directly affects the status of the PBI.

A PBI cannot be "Done" if it has linked "Open" impediments.

Screen Shot:

 Impediment screen shot.

Fields:

Field NameDescriptionData Type
Title A short description of the impediment. Text
Description The detailed description of the impediment. Text
State This is the status of the impediment. Drop Down List
Area The Area Path (AKA Feature Scope) of the impediment. Project Path
Sprint The iteration Path of the impediment. Project Path 
Owned By The current owner of the impediment. Project User

Work flow:

Impediment workflow

Work Item States:

Work Item Links: